3.Electrolyte Factory project ( Same as last week)(1). ShenZhen New Creative Material Technology We visited and discussed with Dr. Wang on October 15th. Dr. Wang revised and provided the document list on October 21th.(2). GeTeCe(Tinci) We had a meeting with GeTeCe(Tinci) on November 5th, updated proposal and provided to us on November 13th.(3). ESM Ton provided a comparison report on December 16. Waiting for final decision. The price of GeTeCe (Tinci) is about RMB 5 million compared with NCM (Dr. Wang).4. NMP condensation and purification(1). TTCL provided their EPC quotation, but we found their price is too high.(2). Waiting fo ESM Ton to push TTCL to provide all of the NMP design information.5. Requirements for equipments installation conditions, schedule of moving in and installation such as attached file.“Equipment schedule 2020-01-03 mass production in March 1, 2021”