Hi Cathy, Unfortunately, US warehouse just informed that there do have all the products ready to ship. The cutoff date for attached booking is 13 Dec (this Fri), hence you have to let me know your decision today. AS657/2 (URC-1906 & URC-1907) production only ready end of next week. AF6300/F (URC-1905) only available on 23rd Dec, we can only ship 216 gal now. Please advise how you want to ship now. Option 1 :Ship order URC-1904 and URC-1905 this week with partial AF6300/F, balance ship end Dec or early January (due to Christmas and New Year holiday) Option 2 :Ship all 4 orders together when everything is available, ETD could be end Dec 2019 early January (due to Christmas and New Year holiday) Also please advise the exact ETA date that the shipping line need to avoid during the CNY period. Thank you.