The change of exterior wall material to 3M film sticker sits with the following factors will affect the project's engineering and progress<br>1, according to the original rban Design Review scheme, there is no need for re-examination, but the construction of how to rely on the approved facade scheme, must seriously consider not causing the current external wall system integrity damage.<br>2, if because of the construction of new external wall materials and reduce the position of the facade opening, it must be re-submitted to all review. 3, facade material changes must also be sent to Urban Design Review, estimated to be two to three months or more time.