Additional information for the missing data from your BOQ as follow:Instrument portion1. only provided instrument index (instrument summary list is preferred), bill of material (cable, wiring, etc.) was not providedPiping portion:1.bill of material of piping support was not providedThanks for receiving your provided preliminary BOQ, after reviewed it, please refer to our queries as follow:Electrical portion:1. The material was only partial, missing MCC panel and grounding material list, etc.Equipment portion:1. Only data sheet for static equipment document , no shop or engineering drawing, KPEC is willing to assist AMITA to survey price in market, we have not be asking to participate in design to produce drawing2. Please indicate which static equipment is belong to “pressure vessel” which defined in Thailand3. If pressure vessel is not purchased in Thailand, we suggest import permit should be arranged by client4. If pressure vessel are oversea made (not by Thailand), any other regulation or rule or spec. need to be follow rather than ASME & AI application?General (Client should have tender document in Procurement and Construction stage):1. To specify scope of work / material supply scope/ tie-in point of boundary limit/ target schedule, etc. for every discipline in procurement and construction stage2. To specify temporary water supply and power supply to be included or excluded during construction stage3. To specify if commissioning is included or excluded ?4. others