A party affected by force majeure shall not be deemed to be in breach of this contract, or otherwise be liable to the other, by reason of any delay in performance, or the non-performance, of any of its obligations under this contract to the extent that the delay or non-performance is due to any force majeure of which it has notified the other party in accordance with Article 12.3.
The time for performance of that obligation shall be extended accordingly, subject to Article 12.4.