There is a problem occurred. The problem is the delivery time.
Would you make a request to FCFC to accept the delivery postpone for 50 days ?
Because of the recovery constructions for the KUMAMOTO after the Earthquake,
many of the materials have been preferentially arranged for these construction.
We are expecting a delay about a few weeks. But to be sure, would you make a request for
50 days extension for us ?
Latest shipping date: August 10, 2016 ⇒ + 50 days extension = September 30, 2016