Dear Cathy and Mei,
This is to ship to KYE factory in DG, and let’s work with them to complete the process required by the time.
And for the delivery schedule for the 100K pcs, the temporary arrangement are:
Let’s start 10K production for KYE to check our quality, ETD: Mid of Jan. (the earlier, the better).
After 10K pcs is OK, please start at least 30K and be ready before CNY.
20K – 3/10
20K – 3/30
20K – 4/30
Anyway, we will finish all 100K before end of Apr. 2016.
Hi Bruce,
Well noted the schedule for 1st 100K order.
We will run our internal process and issue the POs to order all components immediately.
For 1st 10K production, Mei will provide the detailed schedule once we get all information about materials ready date as well as the equipment/jig/testing.
We will pay special attention on the quality of every shipments.